360 East 72nd Street: Working Together For The Benefit All Residents

By
YouTube Preview Image

Recently I wrote a 3 part series on Coop financial statements. In Part 1, we discussed the General Principles of a Coop Corporation and the Telltale signs of a GOOD Building. Part 2 discussed what to look for in Coop Financials. In Part 3 we look at assessing a Coop’s financial condition.

As I pointed out, Coops seldom conduct a study to determine the remaining useful lives of the building’s systems and major components. Additionally, coops are seldom required (if ever) by their governing documents to accumulate funds in advance of the need of such repairs.

Depending on the size of the building, emergency and unplanned repairs can result in a serious increase in maintenance or special assessments. High maintenance and assessments drive down apartment selling prices.

The board did all of this work without raising maintenance or passing a special assessment.

With an Engineering Systems Report, a 5 year Capital Budget Plan and a culture of working together for the benefit of all residents, 360 East 72nd Street was a rare example of a Coop, thanks to its Board, that took a building with serious problems and rebuilt most of the infrastructure….The board did all of this work without raising maintenance or passing a special assessment.

The Costs:

Brick replacements/balconies $8.5 million
A/C chiller $995,000
Oil tank $213,000
35th floor roof $510,000
Elevators (machinery) $510,000
Elevators (cabs) $170,000
18th Floor roof $249,000

Total $11,600,500